Outages

PLANNED OUTAGES

PLANNED OUTAGES

Planned outages occur when Buller Electricity is undertaking construction and maintenance work on the network. Note that if you will be affected by a planned outage you will receive a notification from your electricity retailer.
Our schedule of planned outages is listed below. On occasions we may be unable to proceed with work on the day the planned outage is scheduled due to events beyond our control, such as the weather, or if more urgent fault work needs to be carried out elsewhere. In most cases provision is made for work to be carried out on an alternative day.
In the case of a planned outage cancellation, if time permits you will notified by your electricity retailer, or alternatively please check this webpage or our facebook page. If you have any questions about planned outages, please contact us.

Last Updated: 5/10/2018 7:16 AM

Karamea – Tuesday, 9 October 2018

REASON: Network Maintenance
REFERENCE: BU-PL-132
NO OF OUTAGES: 1
OUTAGE TIME 1: Tuesday, 9 October 2018, 08:30 AM – 04:00 PM
STREETS AFFECTED: All consumers north of Granite Creek
NO OF CONSUMERS: 312
ALTERNATIVE TIME 1: Wednesday, 10 October 2018, 08:30 AM – 04:00 PM

Karamea – Tuesday, 16 October 2018

REASON: 11Kv Maintenance
REFERENCE: BU-PL-134
NO OF OUTAGES: 1
OUTAGE TIME 1: Tuesday, 16 October 2018, 09:00 AM – 03:30 PM
STREETS AFFECTED: Quinlans bridge to Oparara bridge

NO OF CONSUMERS: 23

ALTERNATIVE TIME 1: Wednesday, 17 October 2018, 09:00 AM – 03:30 PM

Karamea – Thursday, 18 October 2018

REASON: Replace arms and hardware
REFERENCE: BU-PL-135
NO OF OUTAGES: 1
OUTAGE TIME 1: Thursday, 18 October 2018, 08:30 AM – 03:30 PM
STREETS AFFECTED: Cemetery at Market Cross to Oparara Bridge via the Oparara Road
NO OF CONSUMERS: 51
ALTERNATIVE TIME 1: Friday, 19 October 2018, 08:30 AM – 03:30 PM